570 Church Street, Melbourne

A creative approach to solving issues with existing floors in heritage buildings across 8,000 m2 of office space in the heart of Melbourne’s suburb of Richmond.

ClientEmleigh Pty LtdBuilderHacer Group Pty LtdPurpose & SizeBase Build Office FitoutDuration6 MonthsCompletedMarch 2017


Key Features and Benefits

570 Church Street was a redevelopment of the existing heritage listed building to achieve a 4 Star NABERS and 5 Star Green Star Rating.

An access floor solution in this heritage building provided the client a solution for a level surface after decades of various floor finishes having being applied to the existing heritage floor.

ASP engineered a solution to the ground floor area with a double height access floor system installed utilising our Rigid Grid System.

Access Floor Systems Used

Steel Cementitious 3.0kN Ultra Fix System,

Steel Cementitious 3.0kN Rigid Grid System,

Calcium Sulphate Interlock System in the amenities and

Steel Cementitious 4.5kN Rigid Grid HPL System.