Westpac Head Office, Sydney

Provide an access floor for the purpose of distributing cables/ data and power throughout the building without the need for cable trays.

Provide computer room floors to several IT and Comms rooms throughout the building.


ClientWestpacBuilderLeighton ContractorsPurpose & SizeCommercial: 72,000m²Duration14 MonthsCompletedOctober 2009

Access Floor System Used:

RAF 01 – SC4.5 Bare Panel
FAF 02 – SC4.5 HPL Rigid Grid system

Project Features and Highlights:

Greater adaptability from 150mm access floors allowing easy reconfiguration of work areas for fit out flexibility and connectivity. ASP supplied the floor boxes with power and data sockets to the project specifications.