Portfolio
ANZ Headquarters - Docklands VIC

Project Size

84,000 m²

Value

$ 8.2 Million

Builder

Bovis Lend lease

Program

Start Date: August 2008

Handover Date: October 2009

Application

RAF 01 – CF Air Tight System

FAF 02 – CF HPL Rigid Grid system

FFH 450mm

Project Synopsis

In order for this project to receive its 6 Green Star award the access floor contractor had to design an air tight access floor system which had a maximum air leakage rate of 0.2l/s/m².

ASP specifically designed the AT system for this project. This system incorporates air tight stringer, air baffle/highway and also air tight bridging stringers that span a max of 1200mm.

Scope of work

Provide an air tight access floor throughout the majority of the building.

Changing the grid of the access floor 4 times on each level, whilst maintaining the maximum air leakage requirement.

Installation of heavy grade data/comms room access floor for smaller communication room throughout the building.