Project Size |
84,000 m² |
|
Value |
$ 8.2 Million |
|
Builder |
Bovis Lend lease |
|
Program |
Start Date: August 2008 Handover Date: October 2009 |
|
Application |
RAF 01 – CF Air Tight System FAF 02 – CF HPL Rigid Grid system FFH 450mm |
|
Project Synopsis In order for this project to receive its 6 Green Star award the access floor contractor had to design an air tight access floor system which had a maximum air leakage rate of 0.2l/s/m². ASP specifically designed the AT system for this project. This system incorporates air tight stringer, air baffle/highway and also air tight bridging stringers that span a max of 1200mm. Scope of work Provide an air tight access floor throughout the majority of the building. Changing the grid of the access floor 4 times on each level, whilst maintaining the maximum air leakage requirement. Installation of heavy grade data/comms room access floor for smaller communication room throughout the building. |
|